Updated 9/6/06

 

Sture Larsson High School Completed  
    modular student center
Project Scope:
New 72’ x 40’ modular student center/library/computer classroom with associated site work
 

McCandless Center - Modernization Completed  
Project Scope:
Remodel interior to provide new Science classrooms
Enclose interior area for resource room / small classroom
Upgrade fire alarm system
Replace all HVAC units

McCandless Center - Relocatables
Completed
 
 
Project Scope:
Relocate one existing relocatable classroom
Provide two new relocatable classrooms
Provide one new relocatable computer classroom
Provide one new relocatable restroom building
Remove and replace basketball court (doubles as fire access)
Provide new landscaping and irrigation for back area

Lincoln High School - Phase 2A and 2B
Completed
   
Project Scope:
Expand End Zone cafeteria and kitchen and add new restrooms
Modernize Special Ed classroom wing and office area
Expand Career Center and Associated Student Body (ASB) office
Convert two classrooms into a new book room
Remodel staff room
Add a new technology classroom to replace English staff offices
Add teaching walls at all classrooms
Remodel Arts Building and expand space
Provide new roofing to Arts Building
Remove and replace all roofing and fascias
 

Lincoln High School Gym Modernization
Completed
 
Project Scope:
New finishes at existing gymnasium
Motorize bleachers
Refinish existing gym floor and repair bleacher operation

Lincoln High School - Phase 2D
     
Start Construction -- September 2006
District Move-In -- Phased (Final -- October 2006)
   
Project Scope:
New gymnasium with restrooms, storage, lobby, Athletic Director offices and student store
Remodel and expand Huddle Cafeteria (no revisions to kitchen area)
Provide new exit corridors through existing locker rooms and modify locker areas as needed
New HVAC for locker rooms
New and upgraded fire alarm system throughout
Add new fire sprinklers throughout new and existing gyms
New irrigation well to replace existing
New student entry plaza and landscaping

  Fall 2006
Brookside Elementary
Start Construction -- September 2006  
District Move-In -- December 2006  
     
Project Scope:
Provide new modular Science classroom on east end of classroom wing including associated site work, demotition and earthwork
Add shade structures including concrete paving and landscaping in the 7/8th grade area
Upgrade electricity to the modular site including power, fire alarm and signal as required
Provide water service to existing portables

Provide Water To Portables  
Completed by January 2007  
Claudia Landeen Elementary  
Don Riggio Elementary  
Mable Barron Elementary  

  Winter 2006 - 2007
Mable Barron Elementary - New Construction  
Start Construction -- 10/02/06 (12/12/06)  
District Move-In -- 8/01/07 (7/09/07)  
Project Scope:
Add new multi-purpose building with outdoor stage
Add masonry wall to conceal existing utility yard
Reconfigure parking area with enlarged circulation and parent drop-off
Add shade structures

Sierra Middle School  
Start Construction -- January 2007
District Move-In -- August 2007
Project Scope:
New administration / library / staff room building
Relocate preschool relocatable and play yard
Add landscaping and wrought iron fencing at front corner of site at Stanton Way
Remodel existing restrooms at classrooms
Reconstruct ADA compliant restrooms at multi-purpose room
Replace HVAC units at existing classrooms and multi-purpose room
Add HVAC units with ducting to Gym

Claudia Landeen Elementary  
Start Construction -- January 2007  
District Move-In -- August 2007  
Project Scope:  
Replace roof including new metal siding and roofing to replace existing wood shingles, upgrade built up roof, and paint plywood soffit on main building
Upgrade HVAC units at existing buildings
Upgrade restrooms
Remodel servery kitchen
Add shade structures
Upgrade site to be ADA compliant
Remodel interior of existing classroom building to create four new classrooms and one Science lab  
Add new concrete ramps and sidewalk to replace nonconforming ramps at remodeled classroom building and second exit for Science lab  

  Spring 2007
Tully C. Knoles Elementary  
Start Construction -- March 2007  
District Move-In -- April 2008  
Project Scope:  
Add new modular classroom building consisting of three classrooms -- which includes a Science lab
Add a new modular restroom building
Relocate three portable classrooms
Re-roof (14,000 sf.)
Upgrade restrooms in the classroom wings
New administration building with accessible restrooms and associated site work
Add new entry plaza with security / ornamental fencing and trellis to highlight entry
Create new delivery / loading area adjacent to existing kitchen including fencing and CMU walls
Demolish existing non-compliant kitchen and storage addition
Upgrade cooking kitchen in multi-purpose room
Modify lighting in multi-purpose room to allow for basketball and add six portable floor mounted backboards
Relocate Pre-K portable and existing play area
Create new accessible concrete ramp to connect classroom wings to existing administration, entrance, and playfields

John R. Williams Elementary
Start Construction -- March 2007
District Move-In -- March 2008
Project Scope:
Add new administration building including a new entry plaza with seating, landscaping, new bike fenced area and new ornamental fencing
Upgrade selected restrooms
Upgrade the parking area including:  reconfiguration of student drop-off, visitor, and staff parking areas, new utilities and kitchen service yard, common space, paving and CMU walls
Remodel kitchen including multi-use room upgrades
Add new cooking kitchen and side-stage curtains
Provide a new modular building containing one classroom and one Science lab
Relocate three existing portable classrooms
New hard-court play area and shade structures
Upgrade roof at classroom wing 'C' only
Upgrade site power, fire alarm and signal pathways

Colonial Heights Elementary  
Start Construction -- May 2007  
District Move-In -- April 2008  
Project Scope:  
New administration building including reception / admin offices, nurse station, and toilet rooms
Expand hard-court at the 6th through 8th grade area
Relocate Speech and Title I spaces
Add new rooftop screens for HVAC equipment at the front of the campus
Upgrade the parking area including:  reconfiguration of student drop-off, visitor, and staff parking areas, new brick wall, ornamental fencing and bike are along the front entrance to the campus
Remodel existing multi-purpose space into cooking kitchen and servery  
Add six new modular classroom buildings  
Relocate Pre-K building, two play areas, and two play structures -- possible new structures  
Relocate two portable classrooms  
Add shade structures at the 7th through 8th grade area  
Upgrade selected restrooms  
Upgrade HVAC units at kitchen  
Remodel 7th / 8th grade Science labs  
Upgrade power, fire alarm and pathways  

  Summer 2007  
Lincoln Elementary  
Start Construction -- July 2007  
District Move-In -- October 2008  
Project Scope:  
Add new administration building and renovate existing library
Add new small parking lot
Upgrade selected restrooms
Upgrade substandard roofing
Upgrade ADA and life safety including fire alarm, power, and signal pathways
Relocate four existing portable classrooms and two storage containers
Add a food serving center within the multi-purpose building  
Remodel staff parking lot and service area -- pending  

  Winter 2007  
Mable Barron Elementary - Modernization  
Start Construction -- January 2008  
District Move-In -- August 2008  
Project Scope:
Convert existing multi-purpose room to the Library / Media Center, computer lab and specialty spaces
Upgrade toilet rooms in main building
Upgrade roof

Village Oaks Elementary
TBD
   
   
     
These scope statements change during the course of the projects due to changing conditions and construction market forces.
revised 09-12-06

 

 